The Power Plant which requires minimum time in starting from cold condition to full-load condition – Power Generation MCQ#62

The Power Plant which requires minimum time in starting from cold condition to full-load condition:

  1. Steam power plant
  2. Gas power plant
  3. Hydro-electric power plant
  4. Nuclear power plant

Correct answer: 3. Hydro-electric power plant

The hydroelectric power plant doesn’t require a long time for putting in service. It can be instantly put on service.